Current:Home > MarketsFederal regulators give more time to complete gas pipeline extension in Virginia, North Carolina -Wealth Evolution Experts
Federal regulators give more time to complete gas pipeline extension in Virginia, North Carolina
View
Date:2025-04-18 01:30:07
RALEIGH, N.C. (AP) — The builders of a proposed natural gas pipeline that will enter North Carolina from Virginia now have another 2 1/2 years to complete the project after federal regulators pushed back a deadline for the work.
The Federal Energy Regulatory Commission approved on Tuesday a request by owners of the proposed 75-mile (121-kilometer) Southgate extension of the Mountain Valley Pipeline to allow for more time for construction, news outlets reported.
According to the previous FERC certificate, the project was supposed to be built and in service six months ago. But permitting problems in North Carolina and Virginia amid legal challenges to the larger Mountain Valley Pipeline meant the owners missed the deadline.
Now, with the FERC’s order, the owners have until June 2026 to complete the MVP Southgate project and bring it into service. More permits still must be secured for construction to occur.
The owners of the project, which includes a consortium of natural gas and energy companies, are pleased with FERC’s decision, project spokesman Shawn Day said.
“At the appropriate time, Mountain Valley intends to pursue all necessary permits and authorizations to complete construction of the MVP Southgate project,” Day wrote in an email.
The Southgate extension will continue pushing gas south from the planned 303-mile (488-kilometer) Mountain Valley Pipeline that will go through West Virginia and Virginia. The extension would run from the main pipeline in Pittsylvania County, Virginia, into Rockingham and Alamance counties in North Carolina.
The future of the pipeline — and thus the extension — appeared uncertain with opposition from environmental groups and some elected officials. But Congress last year essentially ordered the pipeline’s construction as part of the bipartisan bill to increase the debt ceiling. This past summer, federal courts also dismissed a challenge to construction permits for the Mountain Valley Pipeline and allowed construction to resume.
MVP Southgate would be the second pipeline carrying natural gas to enter North Carolina. Project supporters have said additional gas capacity is needed for reliable and affordable energy. Duke Energy also appears to need a supply to shift its coal-fired power plants to natural gas.
Democratic Gov. Roy Cooper and other elected Democratic officials — including U.S. Reps. Kathy Manning and Valerie Foushee of North Carolina and Reps. Jennifer McClellan and Bobby Scott of Virginia — opposed giving more time for the project. The members of Congress sent a letter Monday to FERC expressing concerns about the extension’s impact on the safety of residents and the environment as efforts to move away from fossil fuels continue.
Still, MVP Southgate needs permits from federal and state agencies, such as the U.S. Army Corps of Engineers and the North Carolina Department of Environmental Quality.
Also Tuesday, FERC agreed to a request from the Mountain Valley Pipeline owners to charge higher rates for the gas being shipped through the buried pipeline. The transportation rate is paid by companies that deliver the gas to end users.
The estimated cost of the pipeline is now $7.2 billion, compared to the first projection of $3.7 billion.
veryGood! (98572)
Related
- Head of the Federal Aviation Administration to resign, allowing Trump to pick his successor
- As theaters struggle, many independent cinemas in Los Angeles are finding their audience
- Kristin Cavallari splits with 24-year-old boyfriend Mark Estes after 7 months
- California wildfire flareup prompts evacuation in San Bernardino County
- South Korean president's party divided over defiant martial law speech
- Rebel Wilson Marries Ramona Agruma in Italian Wedding Ceremony
- Over 90,000 Georgia residents sheltering a day after chemical plant fire sends chlorine into the air
- WNBA playoffs: Players to watch in the semifinal round
- Off the Grid: Sally breaks down USA TODAY's daily crossword puzzle, Triathlon
- Handing out MLB's 2024 awards: Shohei Ohtani, Aaron Judge earn MVPs for all-time seasons
Ranking
- Average rate on 30
- No time for shoes as Asheville family flees by boat, fearing they lost everything
- How often should you wash your dog? Bathe that smelly pup with these tips.
- At Climate Week NYC, Advocates for Plant-Based Diets Make Their Case for the Climate
- Sam Taylor
- Attorneys for NYC Mayor Eric Adams seek dismissal of bribery charge brought by ‘zealous prosecutors’
- Trump lists his grievances in a Wisconsin speech intended to link Harris to illegal immigration
- Are digital tools a way for companies to retain hourly workers?
Recommendation
Head of the Federal Aviation Administration to resign, allowing Trump to pick his successor
2025 FIFA Club World Cup final set: Where games will be played in U.S.
Horoscopes Today, September 28, 2024
California governor signs bills to protect children from AI deepfake nudes
The 401(k) millionaires club keeps growing. We'll tell you how to join.
Sister Wives Star Madison Brush Announces Pregnancy News Amid Estrangement From Dad Kody Brown
Exclusive: Kamala Harris campaign launches 'Athletes for Harris'
2025 FIFA Club World Cup final set: Where games will be played in U.S.